The TeamTec Golar OG 200 burns ship's waste oil sludge, sewage sludge and solid refuse at up to 465 kW (400,000 kcal/h). It has a refractory-lined circular combustion chamber with garbage and ash doors interlocked for at least 4 hours after burning, a two-stage Fremo diesel oil burner, a steam/air-atomised sludge burner fed by a Mono dosage valve on a frequency inverter, a 1100 l steam-heated sludge tank with circulating pump, and a flue gas fan with automatic damper keeping the furnace under negative pressure. The manual covers controls and indicators, the function test program, alarms, instrument and controller settings, operating instructions for solid waste, sludge and slagging, daily to yearly maintenance, troubleshooting, and appendices for the burner control, pumps, nozzles and parts lists.

Apasă pe o piesă din model pentru a vedea codul și rolul ei.Deschide simulatorul 3D

Proceduri de întreținere

Burning solid waste

  1. Main switch and Power switch on; inspect the chamber and remove foreign objects. p. 37
  2. Load the waste through the garbage door and close the doors. p. 37
    Oily rags and separator sludge only in small amounts (about 3 kg) and only with the flue gas fan running
  3. Start the flue gas fan and set the damper to Auto: chamber pressure settles near −24 mm WC. p. 37
  4. Set Diesel oil burner to position 1; use position 2 (both stages) if more heat is needed. p. 37
  5. When burnt out, switch off burner and fan; the fan stops after about 4 h cooling, then reload. p. 37

Burning sludge

  1. Heat the sludge tank and drain off water. p. 37
  2. Start the sludge circulating pump and check sludge pressure 0.5–1 bar. p. 37
  3. Set Sludge burner to Auto: fan and diesel burner start, the sludge burner takes over above the set chamber temperature. p. 37
  4. For sewage sludge or very wet sludge use position 1 (diesel burners keep burning); positions 2 and 3 give fixed dosage of about 12 and 14 Hz. p. 38
  5. Switch Sludge burner off to stop; the fan runs about 4 h for cooling. p. 38

Slagging (removing ash)

  1. Make sure all solids are extinguished and the chamber has cooled. p. 38
  2. Start the flue gas fan, set the damper to Manual and close it with CL/OP. p. 38
  3. Open the doors, remove ash and slag with a hoe and clean the bottom air inlets. p. 38
    Heat and cool slowly to protect the refractory

Emergency stop

  1. Inside the room turn Power off; outside push the emergency stop. Burner, fan and pump stop. p. 38
  2. If the chamber is above 200 °C or waste is still burning, restart the flue gas fan as soon as possible. p. 38

Cleaning the diesel oil pump filter

  1. Do this when pressure falls below 11 bar and cannot be adjusted. p. 49
  2. Close the pump suction and return valves and remove the 8 bolts of the end cover opposite the drive. p. 49
  3. Pull out the filter, wash in diesel oil, blow dry, refit with the gasket and reset pressure to 11 bar. p. 49

Intervale de întreținere

ElementCândAcțiuneManual
Combustion chamberDailyRemove ash and slag when cold; clean the bottom air inletsp. 39
Diesel oil and sludge pressureDailyCheck diesel oil 11 bar and sludge 0.5 bar; check pump for leaksp. 39
Photo resistor and air inletsWeeklyClean the photo resistor with a damp cloth; check combustion and cooling air inletsp. 39
Sludge dosage valveWeeklyCheck for leaks and turn the shaft by handp. 49
Burners, belts, refractoryMonthlyClean blast tube, flame scrod and nozzle; check fan belts and refractory; lubricate moving parts; clean spark arresterp. 39
Diesel pump filter, dosage valve, fan bearings6 monthsClean the oil pump filter, check dosage valve rotor and stator, regrease fan bearings (heat resistant grease) and door hingesp. 39
Controls and safety devicesYearlyRun the function/test program and alarm checks, calibrate safety devices, check oil valves and solenoids for leaksp. 39

Defecte și ce trebuie făcut

Specificații tehnice

Max capacity400,000 kcal/h (465 kW)p. 28
Sludge oil capacitymax 55 l/hp. 28
Sewage sludge capacitymax 20 l/hp. 28
Solid waste chargeType II waste up to 400 l per charge every 4–6 hp. 28
Combustion chamber temperaturenormal 850–1200 °C, max 1200 °C at top refractoryp. 38
Flue gas temperaturenormal 200–350 °C, max 400 °Cp. 38
Furnace negative pressure−10 to −30 mm WC (auto set about −24/−25 mm WC)p. 28
Diesel oil burnerFremo H-520-30 K-HF two-stage, 2 × 2.5 gph nozzles, pump Suntec J3-CAB-1002 set to 11 bar (max 14.5)p. 31
Flue gas fan7000 Nm³/h at 200 mm WC, 7.5/8.7 kW, 1450/1740 rpmp. 31
Sludge dosage valveMono SB 14 R5, 0.37 kW, 280–800 rpm via ATV-16 inverter; start speed about 10.5 Hzp. 32
Sludge tank1100 l net, 1650 l total, steam heatedp. 33
Sludge circulating pumpE-JET SRG 102 N, 18 m³/h at 1.5 kp/cm²p. 33
Normal pressuresdiesel oil 11 bar, sludge 0.5–1 bar, steam/air 6–9 barp. 21
Alarm and trip set pointsdraught failure < 5 mm WC, low diesel oil < 5 bar, low sludge < 0.2 bar, low steam/air < 2 barp. 18
Temperature controller u2 (combustion chamber)sludge only at 850 °C, start sludge burner 600 °C, stop burners 1200 °Cp. 23
Door lock / fan cooling timeabout 4 h after burner stopp. 20
Flue gas fan belt10 mm deflection at about 3 kgp. 49

Piese de schimb și coduri de catalog

PiesăCodBuc.Manual
Burner motor ASEA MT 71D2541p. 136
Ignition transformer ZM20/10D2561p. 136
Photo resistor Landis & Gyr QRB1D5871p. 136
Nozzle 2.5 gph 45°D8102p. 136
Ignition cable, 400 mmD8472p. 136
Solenoid valve coil39273p. 141
Fan wheel 160 x 7542001p. 141
Oil pump Suntec J3-CAB-100264041p. 141
Nozzle set 2.5 and 4.5 gph80541p. 141
Pressure switch XMJ-A020781521p. 141
Mono pump SB 14 R5 stator27181p. 89
Mono pump SB 14 R5 rotor27201p. 89
Mono pump mechanical seal92331p. 89
Oil heater heating element 1.5 kW19722021p. 172

Sursa: manualul producătorului „EM-10 INCINERATOR”, 186 pagini. Numerele paginilor se referă la original. Înainte de lucru, verifică manualul de la bord.

Pagina a fost tradusă automat. Codurile de piese, codurile de eroare și paginile sunt ca în original.