2.4.1 Defect reporting system
CoreChemicalLNGLPGOilAsked to: Master, Chief Officer, Chief EngineerWhere: Anywhere, Chief Engineer's Office, Documentation
Do the senior officers know the company procedure for reporting defects in structure, machinery and equipment to the office through the defect reporting system, and is there evidence that every defect has been reported in this way?
In one lineEvery defect raised in the company system, classified, risk-assessed if critical, and tracked to closure with the office.
How to answer
- Explain the defect reporting workflow: who raises it, how it is classified, how it reaches the office and how it is closed
- Show the current open defect list and explain status and planned rectification for each item
- Explain how defects on critical equipment trigger a risk assessment and temporary measures
- Say how the Master and Chief Engineer review the list (e.g. weekly) before sending to the office
What the inspector looks for
- How defects are raised, categorised (critical/non-critical) and sent to the office
- Whether defects seen during the inspection are already in the defect list
- Follow-up: spares requested, temporary measures, target dates
- Link between defect system, PMS and risk assessment for critical equipment
Have ready to show
- Defect list/defect reports in the company system
- PMS records linked to defects
- Spare part requisitions for open defects
- Risk assessments for defects on critical equipment
- Office correspondence on defects
Avoid
- Defects visible on board that are not in the system
- Defects open for a long time with no action or explanation
- Officers unable to explain the reporting procedure