6.3.1 Ballast water management system (BWMS)
Rotational 1ChemicalLNGLPGOilAsked to: Master, Chief Officer, 2nd / 3rd Officer, Chief Engineer, Engineer officersWhere: Engine Room, Main Deck, PumproomOnly if it applies to the ship
Do the Master and officers know how to operate the ballast water treatment system safely under company and maker's instructions, and is the system in good order and used as intended?
In one lineOperate the BWMS per the manual, record every operation and alarm, and report failures to the company and port State before discharging ballast.
How to answer
- Describe how the system treats ballast (filtration plus UV, electrochlorination or chemical dosing) and the steps for ballasting and deballasting, including TRO or UV monitoring and neutralisation
- Explain the hazards and controls: the SDS for chemicals, PPE, ventilation and gas venting, isolation before maintenance, and handling broken UV lamps
- Explain what you do if the system fails: inform the Master and the company, record it in the BWRB, contact the port State before arriving, and follow the contingency measures. Do not discharge untreated ballast unless the port State allows it
- Explain that any bypass is alarmed, logged and reported
- Describe how the BWRB is kept with times, positions, volumes and treatment status
What the inspector looks for
- The type approval certificate, Ballast Water Management Plan, International Ballast Water Management Certificate and Ballast Water Record Book
- BWMS operating records, alarm logs and bypass records that agree with the record book
- Hazards understood: chemical handling, hydrogen or chlorine gas from electrochlorination, UV lamps containing mercury, high voltage
- Actions on BWMS failure as set out in the BWMP contingency measures
- Equipment condition: no leaks, sensors calibrated, filters working
Have ready to show
- Ballast Water Management Plan and IBWM Certificate
- Ballast Water Record Book
- BWMS type approval certificate and maker's manual
- BWMS operation and alarm logs
- Chemical SDS and PPE, if chemicals are used
- Sensor calibration and maintenance records in the PMS
Avoid
- BWMS alarms or bypass events with no explanation or record
- Deballasting with the system bypassed while the BWRB records treatment
- Crew unaware of the chemical or gas hazards
- Overdue sensor calibration or a failure that has not been reported
← 6.2.3 Bunker pipeline system pressure testing6.4.1 Main deck oil or chemical spill clean up equipment →