SeaVint

8.7.7 DP Equipment condition and maintenance

Rotational 2OilAsked to: Master, Chief Officer, 2nd / 3rd OfficerWhere: Bridge, Cargo Control Room, Chief Engineer's Office, Engine Control RoomOnly if it applies to the ship

Is every item of DP equipment in good working order, and is all of it covered by the planned maintenance system?

In one lineAll DP equipment in the PMS and maintained, defects assessed against capability, trials current.

How to answer

  • Explain the DP system configuration and redundancy.
  • Show that each DP component is in the PMS with maintenance done on time.
  • Explain how DP defects are reported, risk-assessed and their effect on operating limits.
  • Show the latest annual DP trials and the pre-operation checks.

What the inspector looks for

  • DP equipment listed in the PMS: thrusters, propellers and rudders, position references (DGPS, relative systems, taut wire), sensors (gyro, wind, motion), UPS, DP controllers, power management
  • Open defects and their effect on DP capability
  • Annual DP trials and pre-field checks
  • Spare parts for critical items

Have ready to show

  • PMS DP equipment list and maintenance history
  • Annual DP trials report
  • DP defect list
  • DP operations manual
  • Critical spares list

Avoid

  • DP items missing from the PMS
  • Open DP defects not risk-assessed
  • Trials overdue